§ 100151

Added by Stats. 2013, Ch. 320, Sec. 1. (AB 797) Effective January 1, 2014.
(a)Subject to the limitations of this article, the authority may utilize the CMGC project delivery method for public transit projects within its jurisdiction.
(b)The authority may enter into a CMGC project delivery method contract pursuant to this article if, after evaluation of the traditional design-bid-build process of construction and of the CMGC project delivery method in a public meeting, the authority makes a written finding that use of the CMGC project delivery method on the specific project under consideration will accomplish one or more of the following objectives: reduce project costs, expedite the project’s completion, or provide features not achievable

through the design-bid-build method. This finding shall be made prior to the authority entering into a CMGC project delivery method contract. In the CMGC project delivery method proposal, the written findings shall be included as part of an application for state funds for a transit project.

Other sections in Article 4 - Construction Manager/General Contractor Project Delivery Contracts

This content is for reference, learning, and study purposes only. All legal text should be verified against the official California Legislative Information website, which is the authoritative source for California law. Data last processed: February 15, 2026.