§ 345

Amended by Stats. 2024, Ch. 713, Sec. 2. (AB 2368) Effective January 1, 2025.
(a)The Independent System Operator shall ensure the efficient use and reliable operation of the transmission grid consistent with the achievement of planning and operating reserve criteria that are no less stringent than those established by the Western Electricity Coordinating Council and the North American Electric Reliability Council.
(b)In furtherance of subdivision (a), the Independent System Operator may amend its tariff, as deemed necessary and subject to approval by the Federal Energy Regulatory Commission through its rulemaking process, to be consistent with subdivision (a).

Other sections in Article 3 - Independent System Operator

This content is for reference, learning, and study purposes only. All legal text should be verified against the official California Legislative Information website, which is the authoritative source for California law. Data last processed: February 15, 2026.