§ 349

Amended by Stats. 2024, Ch. 713, Sec. 3. (AB 2368) Effective January 1, 2025.
(a)The Independent System Operator shall perform a review following a major outage that affects at least 10 percent of the customers of the entity providing the local distribution service. The review shall address the cause of the major outage, the response time and effectiveness, and whether the transmission facility owner or operator’s operation and maintenance practices enhanced or undermined the ability to restore service efficiently and in a timely manner.
(b)(1) If the Independent System Operator finds pursuant to subdivision (a) that the operation and maintenance practices of the transmission facility owner or operator prolonged the response time or was responsible for the outage, the Independent

System Operator may order appropriate sanctions, subject to the Federal Energy Regulatory Commission approving that authority.

(2)(A) If the Independent System Operator finds pursuant to subdivision (a) that the primary cause of the outage was the insufficiency of the electricity supply available to serve the electrical load within its balancing area authority, the Independent System Operator shall post on its internet website the finding and recommendations to prevent future shortfalls and share the finding and recommendations with the commission, the Energy Commission, and the Legislature.
(B)Findings and recommendations submitted to the Legislature shall be provided in accordance with Section 9795 of the Government Code.

Other sections in Article 3 - Independent System Operator

This content is for reference, learning, and study purposes only. All legal text should be verified against the official California Legislative Information website, which is the authoritative source for California law. Data last processed: February 15, 2026.